IBI Group affiliate Giffels, LLC have won first place standing in the Industrial category of Steel Joist Institute 2009 Design Awards. Giffels, LLC / IBI Group acted as Structural Engineer for the Thyssen Krupp Stainless Processing Facility; a $4 billion, world-class, state-of-the-art facility, located in Southern Alabama. When operational the plant will manufacture and process carbon steel and stainless steel for high value applications by manufacturers in the United States, creating 2700 employment opportunities.

Favoured for the innovation and cost-effective structural system used on such a large project, this project was a high qualifier, which subsequently secured the award.

Project details

Project construction cost: $280 million 

Joist cost, including fabrication and erection: $24 million

Size (square feet): 1.27 million 

Roof area using joists (square feet): 1.24 million 

Joist area (square feet): 1.24 million 

Joist engineering to delivery: Approx. 90 days

Joist erection: Approx. 270 days

Project team

Structural engineer: Giffels-IBI Group, and Gulf States Engineering 

Owner: ThyssenKrupp Stainless USA

Architect: Giffels-IBI Group, and Gulf States Engineering
Construction manager: Hargrove 

Steel joist manufacturer: Vulcraft 

Steel detailer: Computer Detailing Inc., Southern Detailing, Protheous, Apel Structural, and C.H. Potter & Company

Steel fabricator: Cives Steel 

Steel erector: Steel City Erecting